Headline: Provisional EU Deal on Charging Infrastructure Approval Timelines

2026-11-27 11:28
1

18 Nov – The European Parliament and Irish Council Presidency reached a provisional agreement under the Grids Package, streamlining permitting for standalone charging stations, energy storage and grid projects.

Key points:

· Standalone charging stations: max. 6-month approval; grid connection: max. 3 months (extendable to 6 months with valid reasons).

· Permit threshold raised from 100 kW to 200 kW. Charging stations ≤1 MW on man-made structures exempt from planning permission.

· Single national online permitting portal; renewables, grid and charging projects designated as projects of overriding public interest.

· Timeline: ENVI/ITRE vote → Parliament & Council adoption → OJEU publication. Member States transpose within 18 months; rules take effect around 2028.


Impact for Manufacturers & Operators

 Shorter site deployment lead times. The new thresholds affect planning for split charging systems and ultra-fast hubs. EU-bound products must still meet AFIR communication standards.