18 Nov – The European Parliament and Irish Council Presidency reached a provisional agreement under the Grids Package, streamlining permitting for standalone charging stations, energy storage and grid projects.
Key points:
· Standalone charging stations: max. 6-month approval; grid connection: max. 3 months (extendable to 6 months with valid reasons).
· Permit threshold raised from 100 kW to 200 kW. Charging stations ≤1 MW on man-made structures exempt from planning permission.
· Single national online permitting portal; renewables, grid and charging projects designated as projects of overriding public interest.
· Timeline: ENVI/ITRE vote → Parliament & Council adoption → OJEU publication. Member States transpose within 18 months; rules take effect around 2028.
Impact for Manufacturers & Operators
Shorter site deployment lead times. The new thresholds affect planning for split charging systems and ultra-fast hubs. EU-bound products must still meet AFIR communication standards.